Highway Construction in Wadena Done for the Season

Perhaps you’ve noticed, but it’s exciting to share that all four lanes are now open on the west segment of Highway 10! This wraps up the second season of this three‑year improvement project.
Highway 10 west of Highway 71
Installed new underground utilities, including storm sewer drainage pipes and structures. Finished expansion work for all four new lanes of new roadway to 620th Ave. near Bluffton. Completed the J‑turn at Co. Rd. 75. Constructed the second half of the roundabout at Co. Rd. 92
Please be aware: there are currently no speed limit signs installed on the west segment of Highway 10. Permanent speed limit signs will be installed at a later date once a speed study is completed. Until then, drivers are urged to slow down, especially when approaching the roundabout, and use extra caution through the area...