Project Faces $102,000 Funding Gap and more than $1.25 Million in Hail Damage

Aug 25
1 min read

by Trinity Gruenberg

The Wadena County Commissioners held their regular meeting on Tuesday, August 18. Commissioner Murlyn Kreklau was absent.

Event Center Project to be Bid

The board discussed the event center remodel, which is nearly ready to go out for bids. Widseth reported that the current cost estimate is about $432,000, while available funding is roughly $330,000, leaving a gap of around $102,000.

The Event Center Committee had recommended moving ahead with bidding to get real market prices before making final decisions on how to close the funding gap.

Architect Trevor Guck from Widseth asked the board to set basic bid parameters: minimum three‑week advertisement, a public bid opening at 1 p.m. on a Tuesday in the courthouse auditorium, and standard insurance and bonding requirements. He also presented two approaches: a traditional timeline that waits for state building plan approval before bidding, or an expedited approach that bids while the state is still reviewing plans, with any required state changes handled by addendum or change order.

The Event Center Committee recommended the expedited route to keep the project moving.

Commissioners, especially Jon Kangas, raised concerns about the unresolved funding shortfall and the risk of bids expiring before money is secured.

Others noted that recent bids on other county projects have sometimes come in under estimates and wanted firm numbers before making a funding decision.

The commissioners approved the expedited bid opening with Kangas opposed...


Comments


Search By Tags

Follow Us

  • Facebook Basic Square
  • Twitter Basic Square
  • Google+ Basic Square

news@inhnews.com

Tel: (218) 756-2131

Fax: (218) 756-2126

310 Main St. W., Clarissa, MN 56440

Benning Printing & Publishing, inc.
bottom of page