Todd County Construction Update
- 10 minutes ago
- 1 min read

CSAH 11 (SP 077-611-036) from the South County Line to TH 27
Work was scheduled to start here on April 22 for pavement surface milling operations and culvert lining repair work.
The road remains open to traffic throughout construction with signage and flaggers present as needed during specific operations.
Upon completion of milling, there will be segments of the highway that will be reclaimed (exist. pavement ground-up with base material below).
Paving is anticipated for early-May with shouldering and striping to follow; with the current schedule all work should be completed by the end of May.
CSAH 2 (SP 077-602-021) from CSAH 11 to TH 28
Work was scheduled to start here on April 29 for culvert lining repair work.
The road will remain open to traffic throughout construction with signage and flaggers present as needed during specific operations.
Pavement surface milling operations were anticipated to be completed the last week of April.
Upon completion of milling, there will be segments of the highway that will be reclaimed (exist. pavement ground-up with base material below).
Paving is anticipated for mid-May with shouldering and striping to follow; with the current schedule all work should be completed by the end of May.
CSAH 4 (CP 77-26-01) Culvert Pipe
Replacement West of 161st Ave. Intersection
Work is scheduled to start here in early-May for culvert pipe excavation and replacement.
The road will have a short-term road closure during work to replace this single culvert pipe.
Once completed, the culvert excavation area will be open with gravel surfacing until asphalt paver patching occurs in mid-May...