The Verndale City Council held their regular meeting on January 11. Council Member Ardith Carr was absent. New council members Tony Stanley and Daryl Jacobson were sworn in.

Water Project

Approved payment 18—final—$5272 for Eagle Construction Company for a total of just over $2.5 million for the water treatment plant construction.

Approved amendment three, for professional services, for the additional costs due to the State Historic Preservation Office creating a “scrapbook” of the current water tower’s history as per state statute for $15,000.

Quotes for the water meters were received. With Maintenance Supervisor Matt Uselman’s blessing, it was decided to award the contract to the Dakota Supply Group for Kamtrup FlowIQ 2250 meters at a cost of $92,636. Uselman explained they won’t have to physically go to the meter locations to take a reading. . .


Click here to subscribe and get the entire story . . .


Search By Tags

Follow Us

  • Facebook Basic Square
  • Twitter Basic Square
  • Google+ Basic Square

news@inhnews.com

Tel: (218) 756-2131

Fax: (218) 756-2126

310 Main St. W., Clarissa, MN 56440

Benning Printing & Publishing, inc.