Feb 14, 20231 minTodd County Commissioners: Solid Waste changes anticipated to be $4.1 million over original cost by Karin L. Nauber karin@inhnews.com The new Transfer Station building design is about 90% complete. The consultant provided an updated...
Nov 22, 20221 minTodd County Board of Commissioners: Transfer Station update is presentedby Karin L. Nauber karin@inhnews.com The board heard an update on the Transfer Station from Supervisor Mike Eberle. He went over several...
Feb 8, 20221 minTodd County Board of Commissioners: $4 million grant for Solid Waste is acceptedby Karin L. Nauber karin@inhnews.com The Minnesota Pollution Control Agency selected Todd County to receive a grant for $4,000,000 (four...
May 11, 20212 minMultiple fires in the areaBrush pile on fire at the transfer station On Monday, May 3, at 6:02 p.m., the Wadena Fire Department was dispatched to a report of a...