Highway 10 construction returns


The Highway 10 reconstruction project is back in full swing as of March 30. The work will take place between Second Street West and County Road 4 through August. The Highway 10 and Highway 71 intersection is closed and rerouted. From now through June work will be done on the eastbound lane with traffic flowing on the westbound lane. From July through August work will be done on the westbound lane. Follow the detour signs.